WaterSpy will run for 3 years, to allow enough time for all development & integration tasks, but also for the appropriate validation of the approach. The work plan has been structured in such a way, as to achieve quick delivery of the first results and allow a gradual validation of the approach in different situations. WP overlapping has been planned in order to avoid delays in case of a single task being delayed due to unforeseen reasons. WP interconnection is shown in Figure 15. WP1 and WP8 are umbrella work packages, running in parallel with all activities throughout the project. WP2 is the first technical work package and provides input to the main technical WPs (WP3-4-5). Those three WPs are responsible for delivering all WaterSpy device modules. These modules are used as an input to WP6, which will deliver the integrated WaterSpy device. Finally, the final, integrated and lab tested version of the WaterSpy device is used for the field validations in WP7.

WP1 Project Management

Leader: CyRIC

WP1 is the management work package. This is an umbrella WP, running throughout the project’s lifetime.

WP2: System specifications, use case requirements and conceptual design

Leader: NTUA

WP2 deals with the preparation of the system requirements and with its conceptual design. Current practices, user needs and pilot site details will be collected and analysed. This WP sets also the evaluation metrics for the system at a preliminary level. All requirements are used to prepare the preliminary, conceptual design of the WaterSpy system. Finally, the system technical specifications will be delivered through this WP.

WP3: Quantum cascade lasers development

Leader: ALPES

WP3 deals with the design and development of the quantum cascade lasers used as the light sources in the WaterSpy detection system. This is one of the most important technical work packages were the core photonics technology will be developed. The tuneable QCLs will be here developed and tested.

WP4: Photodetectors development

Leader: VIGO

WP4 is responsible for the delivery of the photodetectors. The highly sensitive WaterSpy photo-detectors will be here developed, tested and integrated with the laser sources for combined tests. This is also a key core photonics development WP.

WP5: WaterSpy device subsystems development

Leader: TUW

WP5 is related to the development of the ATR spectroscopy configuration and of all those sub-systems that will allow the automated operation of the WaterSpy device. In particular, the sample pre-concentration subsystem is here developed. The microfluidic configuration is also developed within this WP. Another activity of this WP will be the development and production of the specific antibodies against the single strains of bacteria selected, as well as their integration on the surface. Finally, the WaterSpy device processing electronics are here designed and developed, including the necessary firmware. Those are necessary to perform the data acquisition and pre-processing operations, as well as for communicating with the TRITON system.

WP6: System integration and testing

Leader: AUG

WP6 is the integration WP. Integration in WaterSpy is seen as a parallel process rather than a static task of putting together all developed modules. Thus, it runs in parallel with all main development WPs (WP3-WP4-WP5), in order to make sure that specifications are followed and all modules are developed in compatibility with each other. Testing of the system in the lab is also dealt through this WP.

WP7: Field validation

Leader: IREN

WP7 is responsible for the field testing activities. The device performance is also fully validated through this WP through comparisons with the golden standards systems. An impact assessment and usability analysis report for the device will also be here prepared.

WP8: Dissemination and Exploitation

Leader: NTUA

WP8 is the Dissemination and Exploitation work package, which is also an umbrella WP running throughout project lifetime. A dissemination and exploitation plan will be delivered in M6 and will be updated every six months, Dissemination of results is obviously more active during the second half of the project, where the approach will be tested and validated. Results exploitation and patenting are also dealt through this WP.

Interrelation between the Work Packages and the Tasks of the WaterSpy project (PERT chart).